Northside Carpeting

The hum of machines has ceased,

And the Southwest Library is at peace,

With its fresh, new carpet underfoot,

It's time to move to the next pursuit.


Now the Northside Library takes the lead,

A new project to fulfill their need,

With the same passion and dedication,

The workers start their new formation.

-Written by ChatGPT


Northside Phases

As you can see, there will be 3 phases to the project, with the west side of the building being completed first, then the east, and finally, Main Street. The timeline is still in the works; however, here is a rough draft of what we expect.

  • Now to Late April:
    • Walk through with carpet and shelf mover contractors on the final details of what's going where
    • Maint Team: Remove short shelving on the West side
    • Maint Team: Move the teen shelving to the East
    • Branch Team: Move tables & chairs
    • Shipping of new desk, computer table, and print release station table
  • May 1: West side gets new carpet (Phase 1)
  • May 5 to 8:
    • Maint Team & CNS: Move computers to new desks on the west side
    • Shelf Movers: Move old "Teen stacks" to the west side
    • Shelf Movers: Move stacks from the east side to the center
  • May 9: East Side gets new carpet (Phase 2)
  • May 16: Shelf Movers: Move stacks in the center to the east side
  • May 17: Main Street laminate flooring (Phase 3)
  • May 25 & 26:
    • Maint Team: New circulation desk installed
    • CNS: Move print release and copy stations
    • Maint Team: Removal of the old service desk
    • Shelf Movers: Final shelving moves