Here's what's scheduled over the next 2 weeks.
- Partition track will be installed
- Balance of drywall work will be completed once the partition track is installed.
- Drywall taping/finishing is going to start on Wednesday, July 15, 2020
- Aluminum framing and glazing is to start the week of July 13, 2020
- Millwork will be delivered week of July 13. 2020
- Plumbing rough-in will be complete by Wednesday, July 15, 2020
- Electrical rough-in is on-going
Then all that's left is installing the partition walls (room dividers like we have in the old activities room, only prettier) and finishing the HVAC. The partition walls is delayed and won't get here until the end of August but otherwise we'll have a new activities room shortly!
Thanks for your patience with the dust and noise. You're going to love the finished product!
Barb