Thursday, April 6, 2023

Northside Carpeting Update

There is a small scope change with the Northside Library Carpet Replacement project; we are now doing all of the adult stacks section. This will give a nice refresh to the library and keep the carpet more uniform throughout. Below is an image to help identify the sections that will be worked on, and a timeline of the happenings.  
May 1 to 3: The carpet will be replaced in Section 1
May 4: Computers and other equipment will be moved from Section 2 to Section 1
May 5: The stacks in Section 3 will be moved to Sections 1 and 2
May 8 to 11: The carpet in Section 3 will be replaced
May 12: The stacks in Section 4 will be moved to Section 3
May 15 to 17: The carpet in Section 4 will be replaced
May 18 & 19: The stacks in Sections 1, 2, and 3 will be moved to their new locations
May 22 to 25: The Laminate flooring (LVD) will be installed in Section 2
May 26: Final stack moves, new service desk install, and removal of the old service desk

A couple of things to remember: 
  • The library will open to the public at 3 pm.
  • No curbside service will be available during the closed time. 
  • Brandi will provide signs to be used during the construction with the hours.
  • Even though we should be finished by May 26, we will be telling patrons by the end of the month. Unforeseen circumstances can delay the project, and it's better to re-open to the public ahead of schedule than later. 


No comments:

Post a Comment

KPL STAFF BLOG FINAL EDITION

Thanks to Jason Rimkus for taking four hours of Opening Day footage and crafting a lovely 10 minute video. Bravo! This week's Bright S...