Thursday, September 25, 2014

Southwest Powerwall Project Plan

Some of you may be wondering what's going on with the power wall project at SW. Don't worry, we have a plan. Here's a task list and timeline for those of you who may be interested.


SOUTHWEST POWERWALL PROJECT

What                                                                 Responsibility                                   By When

Children’s banner color selected
Shimon
9/18
Banner above new books designed and ordered
Shimon
9/25
New Books Signage designed and ordered
Shimon
9/25
Children’s banner painted
Maintenance
10/4
Top shelf for power wall ordered
Chuck
9/25
Plants moved from children’s doorway to SW lobby
Maintenance
10/2
Benches ordered for in front of power wall
Barb
9/30
Display units ordered
Barb
9/30
Banner above new books installed
Shimon
10/15
New books signage installed
Shimon
10/15
All shelving installed for powerwall
Maintenance
10/15
Ebook monitor attached to wall
CNS
10/16
Motif designed and ordered for children’s glass doors
Shimon
10/16
Display units installed
Maintenance
11/5
Top shelf added to power wall shelving
Chuck
11/5
 Books transferred to wall
 Circ
 11/6

 